@mmd-toolkit/gantt-no-undef ​

Disallow a task id in click, after, or until that is the id of no task.

✅ The recommended configuration enables this rule.

click names the tasks that it makes links, after names the tasks after which a task starts, and until the tasks at whose start a task ends. When an id is that of no task, mermaid.js gives no error: click makes no task a link, and after and until put the start or the end of the task at today's date. A misspelled id moves the task to today.

Rule Details ​

This rule applies to Gantt charts (gantt). It reports each id in click, after, or until that no task in the chart has.

Explicit task ids and the ids that mermaid.js assigns, such as task1, count as defined, and comparisons are case-sensitive. With three items after the tags, the first is the task id; with one or two, mermaid.js assigns task1, task2, and so on in text order. A task with four or more data items has no id.

after is checked in the start item, the first of two items or the second of three; until is checked in the end item, the last of one to three. Both must be lower case and followed by whitespace. Their ids consist of ASCII letters, digits, _, -, and spaces, and are split at spaces: after a.1 names a and is reported even when a task has the id a.1, and so does after a設計; a tab between ids ends the list.

after or until followed by no such character, as in after 設計, is not reported: mermaid.js reads the item as a date, cannot read it, and does not draw the chart. After a2, Until b1, and data with four or more items are not checked either. Tasks defined later count as defined, including for click, although a click before its task does nothing in mermaid.js.

Examples of incorrect code for this rule:

mmd
%% eslint @mmd-toolkit/gantt-no-undef: error
gantt
  dateFormat YYYY-MM-DD
  Design : des1, 2024-01-06, 3d
  click 
des2
href "https://example.com"
mmd
%% eslint @mmd-toolkit/gantt-no-undef: error
gantt
  dateFormat YYYY-MM-DD
  Design : des1, 2024-01-06, 3d
  Build : 
after des2
, 5d
mmd
%% eslint @mmd-toolkit/gantt-no-undef: error
gantt
  dateFormat YYYY-MM-DD
  Design : des1, 2024-01-06, 3d
  Review : 2024-01-01, 
until des2

Examples of correct code for this rule:

mmd
%% eslint @mmd-toolkit/gantt-no-undef: error
gantt
  dateFormat YYYY-MM-DD
  Design : des1, 2024-01-06, 3d
  Build : after des1, 5d
  click des1 href "https://example.com"

Options ​

This rule has no options.

Further Reading ​

Version ​

This rule was introduced in @mmd-toolkit/eslint-plugin v0.1.0.